Week 2 Progress

This week went as planned. All of the Wiis got stripped down and homebrewed, the last wires were cut, the circuit boards I wanted to test got tested, and the front boards now have all of their wires attached. Attaching the wires took longer than I’d expected, so I may need to rearrange my schedule a bit to put more time into that part of the build.

20210116_221056.jpg


This next week the plan is to assemble the remaining USB boards, the remaining voltage regulation boards, relocate the NAND chips on the other Wiis that need to be trimmed, attach wires to two more types of boards, and end the week by cutting up the Wii boards. It’s definitely the most packed week I’ve scheduled out, so some of it may need to be pushed back if things don’t go well.

Previous
Previous

Progress For Week 3

Next
Next

Progress For Week 1 of 2021